Construction Update - July 2007
Reeves Middle School
Modernizations and additions will be complete by the start of the 2007-2008 school year, increasing student capacity from 525 to 567. Additions include a new entry lobby, administration area, choir room, three new science classrooms and a new library. Except for the gym and the 1998 cafeteria and auxiliary gym additions, the entire building is being modernized, with new electrical and mechanical systems. Technology improvements include wireless internet, a new computer lab, and ceiling mounted overhead projectors. The football/soccer field has been reconstructed and will be ready for use by the start of the school year.
- Total Project Cost: $13.8 million
- Contractor: Babbit Neuman Construction Company
- Architect: BLRB Architects, Tacoma, WA
- OSD Project Manager: John McLaren, AIA
Pioneer Elementary School
Pioneer will be completed by the beginning of the 2007-2008 school year. The work at Pioneer includes all new classrooms (we previously had 13, including kindergarten; we will now have 16, including 2 kindergarten), all new Library with vaulted ceiling space, all new Administration area, and a new covered entry to the school. Pioneer Elementary School also will have wireless internet access.
- Contractor: Porter Brothers Construction, Edgewood, WA
- Architects: BLRB Architects, Tacoma, WA
- OSD Project Manager: Tim Byrne, AIA
Capital High School East Field
The football field is being reconstructed and will be ready for use in September of 2008. Improvements include track resurfacing and reconstruction of the high jump area. The field has been stripped, irrigation systems and drainage installed and new sand base. The project is on schedule.
- Contractor: KBH Construction
Remaining 2003 Bond Track and Field Projects
- Olympia High School: Henderson Street - Reconstruction scheduled for Summer, 2008
- Marshall Middle School - Reconstruction scheduled for Summer, 2008
Completed Construction Projects
Capital High School Modernization and Additions
- Completed in September, 2006
- Total Project Cost: $24.2 million
- Contractor: Berschauer Phillips Construction Company, Olympia, WA
- Architect: BLRB Architects, Tacoma, WA
- OSD Project Manager: John McLaren, AIA
Washington Middle School Modernization and Additions
- Complete in September 2006
- Total Project Cost: $17.0 million
- Contractor: Porter Brothers Construction, Edgewood, WA
- Architect: Mahlum Associates, Seattle, WA
- OSD Project Manager: Tim Byrne, AIA
L.P. Brown Elementary School Modernization and Additions
- Completed in July, 2006
- Total Project Cost: $6.2 million
- Contractor: Babbit Neuman Construction Company, Steilacoom, WA
- Architects: Erickson McGovern Architects
- OSD Project Manager: John McLaren, AIA
Knox Center Gymnasium
- Completed in November, 2004
- Architects: Thomas Cook Fitzgerald Architects
- OSD Project Manager: Tim Byrne, AIA
Ingersoll Stadium Improvements
- Completed in November, 2005
- Architects: BLRB Architects, Tacoma, WA
Completed Track and Field Projects
- Capital High School West Field (JV baseball and soccer)
- Ingersoll Field and Track Resurfacing
- Olympia High School North Street
- Olympia High School JV Field
- Jefferson Middle School North Field (football and soccer)
- Jefferson Middle School South Fields (fast pitch and soccer)
- Reeves Middle School Main Field (football and soccer) ready for use in September 2007